Augusta Approves $596K for Detention Center Fire Safety and Roof Repairs
The Augusta Commission approved $596,288 for repairs at the Richmond County jail. Commissioners agreed to spend $538,001 to replace the fire alarm system. They also set aside $58,287 to fix…

The Augusta Commission approved $596,288 for repairs at the Richmond County jail. Commissioners agreed to spend $538,001 to replace the fire alarm system. They also set aside $58,287 to fix parts of the roof at the Charles B. Webster Detention Center.
Why the fire alarm project? A recent inspection found problems. Big problems. The inspection revealed "a large percentage of device failures and deficiencies" and an "incompatibility between fire alarm panels," per The Augusta Chronicle. Two expansions at the facility added hundreds of different pull-for-emergency fire alarms, emergency control devices and power supplies throughout the building, creating a patchwork of systems that don't always work together.
Basesix Systems won the contract. The Marietta company wasn't the lowest bidder, but they had something better: experience. The firm showed more experience working with the Notifier brand of the jail's fire alarm system, Richmond County Sheriff's Maj. Chester Huffman said in a July 17 memo to Andy Penick, the city's procurement department director.
Choosing a different fire alarm platform would create "potential technical and operational risks," Huffman said.
The detention center was built in 1997 but has undergone two expansions since then. The roof repairs will cover the original buildings and corridors, which have weathered nearly three decades of Georgia storms.
Augusta voters approved an $85 million jail renovation in May. The project was among several identified in the newest version of the special-purpose local option sales tax. Plans would add 300 new inmate beds in the chronically overcrowded facility, which struggles to house its current population.